ECRL project slightly behind schedule due to MCO — transport minister | The Edge Markets

Do you want to share?

Do you like this story?

The East Coast Rail Link (ECRL) project is slightly behind schedule at 23.96% completion as of
31st August 2021 due to movement control restrictions. For Section A from Kota Baru to
Dungun, which includes six stations, the progress currently stands at 11.59%, which is behind
the progress schedule of 12.01%. For Section B from Dungun to Temerloh, the progress is
slightly ahead of schedule at 28.04% while for Section C from Temerloh to Pelabuhan Klang, the
Government is still studying the best alignment to ensure optimal multiplier effects on the local
economy.