Friday, 22 October 2021

RM220 million bridge linking Selangor and Perak ready in May 2025

To be built from January 2022 and slated for completion in May 2025, a 2.04 kilometres bridge
with an allocation of RM220 million will be built across Sungai Bernam to link to Sungai Air
Tawar, Selangor and Pekan Hutan Melintang, Perak. The project will shorten travel from 40
minutes to 10 minutes using normal routes and will be a catalyst for local economic growth.

RM220 million bridge linking Selangor and Perak ready in May 2025

Tuesday, 19 October 2021

Sabah's Pan Borneo Highway project is running smoothly

About 60% of the 12 work packages for Sabah's Pan Borneo Highway (PBH) project have
commenced as of September 2021. A letter of acceptance for three new work packages from
Sandakan Mile 32 to Sungai Baoto had also been issued and works are expected to begin this
year. The Sabah PBH project consists of three phases whereby Phase One was given priority
for implementation, thereby totalling 706km and divided into 35 work packages.

Sabah's Pan Borneo Highway project is running smoothly

Kuala Lumpur-Iskandar Puteri HSR: Study done and will be submitted to Cabinet, says Mustapa | EdgeProp.my

The study on the proposed Kuala Lumpur-Iskandar Puteri High Speed Rail (HSR) project has been done and is set to be submitted to the Cabinet, economic affairs minister Mustapa Mohamed revealed in a FMT report today.

We’re just waiting for it to be submitted to the Cabinet,” Mustapa said during a question-and-answer session at Invest Malaysia 2021 today.

He added that another proposal to link the HSR to Bangkok, Thailand was at a “very early” stage.

Mustapa also touched on the MRT3 project which had “received several proposals and presentations”.

Kuala Lumpur-Iskandar Puteri HSR: Study done and will be submitted to Cabinet, says Mustapa | EdgeProp.my

New Meru Raya-Klebang road to ease traffic jam | The Star

New Meru Raya-Klebang road to ease traffic jam | The Star

A new road connecting Meru Raya and Klebang will be built to reduce traffic congestion in both
towns. The RM6.4 million project would connect Lebuh Chepor Utama 2 in Meru Raya and
Lebuh Klebang Putra in Klebang. The project would consist of four connecting roads and a
bridge across Sungai Klebang. The project will begin at the end of the 2021 and is expected to
be completed within 18 months.

Tuesday, 12 October 2021

ECRL project slightly behind schedule due to MCO — transport minister | The Edge Markets

The East Coast Rail Link (ECRL) project is slightly behind schedule at 23.96% completion as of
31st August 2021 due to movement control restrictions. For Section A from Kota Baru to
Dungun, which includes six stations, the progress currently stands at 11.59%, which is behind
the progress schedule of 12.01%. For Section B from Dungun to Temerloh, the progress is
slightly ahead of schedule at 28.04% while for Section C from Temerloh to Pelabuhan Klang, the
Government is still studying the best alignment to ensure optimal multiplier effects on the local
economy.

ECRL project slightly behind schedule due to MCO — transport minister | The Edge Markets

Phase 1 of MRT Putrajaya line to open in November, Phase 2 now 93.52% completed | The Edge Markets

Phase 1 of the MRT (Mass Rapid Transit) Putrajaya Line (covering the stretch between the
Kwasa Damansara and Kampung Batu stations) is 99.9% completed and is expected to open in
November 2021. Phase 2 (from the Kentonmen to Putrajaya Sentral stations) is 93.52%
completed and is expected to become operational in January 2023.

Phase 1 of MRT Putrajaya line to open in November, Phase 2 now 93.52% completed | The Edge Markets

Central spine road, a game-changer for Pahang Barat, says ECERDC | The Edge Markets

The Central Spine Road will reduce the travel distance between the East and West Coast of
Peninsular Malaysia and open up new areas of economic activity and investment in the vicinity.
The project will span from Bentong, Pahang to Kuala Krai, Kelantan and Kota Bharu-Kuala Krai
Highway and is reportedly scheduled to be completed by 2025.

Central spine road, a game-changer for Pahang Barat, says ECERDC | The Edge Markets

Sunday, 13 October 2019

National Transport Policy (NTP) to be launched on October 17



KUALA LUMPUR (Oct 8): The government will unveil the National Transport Policy (NTP) — a blueprint for the transport sector for 2019 to 2030 — on Thursday, Oct 17.

The NTP's vision is to develop a sustainable transport sector that accelerates economic growth and supports the wellbeing of the rakyat in line with an advanced nation status.

"This is the first time we have a strategic plan for the transport sector," said Deputy Transport Minister Datuk Kamarudin Jaffar at a media briefing on the NTP here today.

The NTP, covering air, land and sea transport, will be driven by five policy thrusts and 23 strategies.

The first policy thrust aims to strengthen the governance to create a conducive environment for the transport sector.

The second is to optimize, build and maintain transport infrastructure, services and networks to maximize efficiency.

The third is to enhance safety, integration, connectivity and accessibility for seamless journey.

The fourth is to advance towards a green transport ecosystem and the fifth is to expand the global footprint and promote the internationalization of transport services.

The NTP will be launched by Prime Minister Tun Dr Mahathir Mohamad.

Source: https://www.theedgemarkets.com/article/national-transport-policy-be-launched-oct-17